Reduce soot-blower steam consumptionPaiton, Indonesia

Major Indonesian power plant reduces CO2 emissions with alternative for steam soot blowers (Paiton/Jawa)

Soot blower steam consumption reduced by 65% — back-pass flue gas temperature reduced by 10 °C with saving of 13,000 t coal/yr

Paiton, Indonesia

The Paiton power plant operated by YTL is the biggest power producer in Indonesia. The ABB / GE type 2 pass boilers are equipped with steam soot blowers. Since August 2022, have been installed four P-WAVE generators at the #50 boiler in the back-pass / economizer section of boilers. The generators are operated once per hour at 600–750 bar. This performance upgrade allowed the plant to reduce back-pass flue gas temperature by 10 °C and soot-blower steam consumption by 67%. Base on this success story, a similar follow-up order for boiler #60 was placed in 2024.

Plant schematic (pulverized coal fired power plant)

Paiton - schematic.jpg

Source: https://www.jawapower.co.id/the-power-station/production-process

Positions in backpass (economizers)

Installed P-WAVE generators

Paiton - installation.jpg